Seamless Steel Pipe Process under Modernization
|
|
Pyongyang, March 15 (KCNA) -- The Chollima Steel Complex in the DPRK has pushed ahead with the modernization of seamless steel pipe process by introducing high-temperature air-combustion technology based on anthracite gasification, as part of the efforts to strengthen the independence and Juche character of metal industry. It is said that the production of seamless steel pipe will be put on a normal basis without using heavy oil and the control system for production process on a technically higher level after modernization. A design for remodeling heating furnace was completed in a short span of time together with the dismantlement of waste-heat boiler. Now, the complex is pushing ahead with technical preparations and manufacture of equipment like gas pipe. |